The correct answer is A. The contract is being negotiated. See the full explanation below for the reasoning.

Question

A plan for managing the end of a supplier contract should be created when?

Options

  • AThe contract is being negotiated
  • BThe contract is about to be ended
  • CThe Supplier Manager decides that there is a risk the contract might need to end soon
  • DThe contract has been agreed