BCS-ISEB
ISEB-ITILF · Question #196
Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for…
The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.
Question
Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures
Options
- A1, 2 and 3 only
- BAll of the above
- C1 and 3 only
- D2 and 4 only
How the community answered
(72 responses)- A83% (60)
- B10% (7)
- C4% (3)
- D3% (2)
Community Discussion
No community discussion yet for this question.