Which of the following are valid parts of the service portfolio? 1. Service pipeline 2. Service knowledge management system (SKMS) 3. Service catalogue
The correct answer is C. 1 and 3 only. See the full explanation below for the reasoning.
Question
Which of the following are valid parts of the service portfolio? 1. Service pipeline 2. Service knowledge management system (SKMS) 3. Service catalogue
Options
- A1 and 2 only
- B3 only
- C1 and 3 only
- DAll of the above
How the community answered
(56 responses)- A7% (4)
- B13% (7)
- C77% (43)
- D4% (2)