In a business activity model, which of the following type of activities respond to deviations between actual and planned performance?

The correct answer is C. Controlling activities. See the full explanation below for the reasoning.

Question

In a business activity model, which of the following type of activities respond to deviations between actual and planned performance?

Options

  • AMonitoring activities.
  • BDoing activities.
  • CControlling activities.
  • DPlanning activities.

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    11% (4)
  • C
    80% (28)
  • D
    6% (2)