It is unclear to a project sponsor why a particular requirement has been included in a recently released version of a system. Which of the following will allow him to identify who originally asked…

The correct answer is B. The source of the requirement. See the full explanation below for the reasoning.

Question

It is unclear to a project sponsor why a particular requirement has been included in a recently released version of a system. Which of the following will allow him to identify who originally asked for the requirement?

Options

  • AThe validation of the requirement.
  • BThe source of the requirement.
  • CThe resolution of the requirement.
  • DThe justification of the requirement.

How the community answered

(54 responses)
  • A
    13% (7)
  • B
    78% (42)
  • C
    4% (2)
  • D
    6% (3)