IIA-CIA-PART3 · Question #84
Which of the following controls would an internal auditor consider the most relevant to reduce risks of project cost overruns?
The correct answer is D. There is a formal process to monitor the status of the project and compare it to the cost baseline. You've hit your session limit · resets 10:20pm (America/New_York)
Question
Which of the following controls would an internal auditor consider the most relevant to reduce risks of project cost overruns?
Options
- AScope change requests are reviewed and approved by a manager with a proper level of authority.
- BCost overruns are reviewed and approved by a control committee led by the project manager.
- CThere is a formal quality assurance process to review scope change requests before they are
- DThere is a formal process to monitor the status of the project and compare it to the cost baseline
How the community answered
(38 responses)- A3% (1)
- B5% (2)
- C8% (3)
- D84% (32)