With regard to disaster recovery planning, which of the following would most likely involve stakeholders from several departments?
The correct answer is B. Prioritizing the order in which business systems would be restored. You've hit your session limit · resets 10:20pm (America/New_York)
Question
With regard to disaster recovery planning, which of the following would most likely involve stakeholders from several departments?
Options
- ADetermining the frequency with which backups will be performed.
- BPrioritizing the order in which business systems would be restored.
- CAssigning who in the IT department would be involved in the recovery procedures.
- DAssessing the resources needed to meet the data recovery objectives.
How the community answered
(37 responses)- A3% (1)
- B81% (30)
- C11% (4)
- D5% (2)
Explanation