nerdexam
IIA

IIA-CIA-PART3 · Question #184

With regard to disaster recovery planning, which of the following would most likely involve stakeholders from several departments?

The correct answer is B. Prioritizing the order in which business systems would be restored. You've hit your session limit · resets 10:20pm (America/New_York)

Question

With regard to disaster recovery planning, which of the following would most likely involve stakeholders from several departments?

Options

  • ADetermining the frequency with which backups will be performed.
  • BPrioritizing the order in which business systems would be restored.
  • CAssigning who in the IT department would be involved in the recovery procedures.
  • DAssessing the resources needed to meet the data recovery objectives.

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    81% (30)
  • C
    11% (4)
  • D
    5% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Community Discussion

No community discussion yet for this question.

Full IIA-CIA-PART3 Practice