A company produces water buckets with the following costs per bucket: Direct labor = 82 Direct material = $5 Fixed manufacturing = 83.50 Variable manufacturing = 82.50 The water buckets are usually…
The correct answer is A. $9.50. You've hit your session limit · resets 10:20pm (America/New_York)
Question
A company produces water buckets with the following costs per bucket:
Direct labor = 82 Direct material = $5 Fixed manufacturing = 83.50 Variable manufacturing = 82.50 The water buckets are usually sold for $15. However, the company received a special order for 50.000 water buckets at 311 each. Assuming there is adequate manufacturing capacity and ail other variables are constant , what is the relevant cost per unit to consider when deciding whether to accept this special order at the reduced price?
Options
- A$9.50
- B$10.50
- C$11
- D$13
How the community answered
(39 responses)- A82% (32)
- B10% (4)
- C5% (2)
- D3% (1)