An organization created a formalized plan for a large project. Which of the following should be the first step in the project management plan?

The correct answer is A. Estimate time required to complete the whole project. You've hit your session limit · resets 10:20pm (America/New_York)

Question

An organization created a formalized plan for a large project. Which of the following should be the first step in the project management plan?

Options

  • AEstimate time required to complete the whole project.
  • BDetermine the responses to expected project risks.
  • CBreak the project into manageable components.
  • DIdentify resources needed to complete the project

How the community answered

(27 responses)
  • A
    81% (22)
  • B
    4% (1)
  • C
    4% (1)
  • D
    11% (3)

Explanation