associated with level 4 of the business process method?

The correct answer is A. Activity. See the full explanation below for the reasoning.

Question

associated with level 4 of the business process method?

Options

  • AActivity
  • BSubprocess
  • CMajor process
  • DMega process

How the community answered

(21 responses)
  • A
    71% (15)
  • B
    5% (1)
  • C
    10% (2)
  • D
    14% (3)