An organization has an agreement with a third-party vendor to have a fully operational facility, duplicate of the original site and configured to the organization's needs, in order to quickly…

The correct answer is C. Storage area network recovery plan. You've hit your session limit · resets 10:20pm (America/New_York)

Question

An organization has an agreement with a third-party vendor to have a fully operational facility, duplicate of the original site and configured to the organization's needs, in order to quickly recover operational capability in the event of a disaster, Which of the following best describes this approach to disaster recovery planning?

Options

  • ACold recovery plan,
  • BOutsourced recovery plan.
  • CStorage area network recovery plan.
  • DHot recovery plan

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    83% (20)
  • D
    8% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)