A organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000. In this scenario, the organization agreed to which of the following types of contracts?

Options

  • AA cost-reimbursable contract.
  • BA lump-sum contract.
  • CA time and material contract.
  • DA bilateral contract.

How the community answered

(50 responses)
  • A
    14% (7)
  • B
    74% (37)
  • C
    4% (2)
  • D
    8% (4)

Explanation