IIA-CIA-PART3 · Question #3

An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how…

The correct answer is B. A quality audit. See the full explanation below for the reasoning.

Question

An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how project tasks are completed?

Options

  • AA balanced scorecard.
  • BA quality audit
  • CEarned value analysis.
  • DTrend analysis

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    83% (19)
  • C
    4% (1)
  • D
    9% (2)