IIA-CIA-PART3 · Question #3
An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how…
The correct answer is B. A quality audit. See the full explanation below for the reasoning.
Question
An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how project tasks are completed?
Options
- AA balanced scorecard.
- BA quality audit
- CEarned value analysis.
- DTrend analysis
How the community answered
(23 responses)- A4% (1)
- B83% (19)
- C4% (1)
- D9% (2)