IIA-CIA-PART3 · Question #291
An organization contracted a third-party service provider to plan, design, and build a new facility. Senior management would like to transfer all of the risk to the builder. Which type of…
The correct answer is A. Cost-plus contract. You've hit your session limit · resets 10:20pm (America/New_York)
Question
An organization contracted a third-party service provider to plan, design, and build a new facility. Senior management would like to transfer all of the risk to the builder. Which type of procurement contract would the organization use?
Options
- ACost-plus contract.
- BTurnkey contract.
- CService contract.
- DSolutions contract.
How the community answered
(34 responses)- A74% (25)
- B15% (5)
- C9% (3)
- D3% (1)