Question

An organization contracted a third-party service provider to plan, design, and build a new facility. Senior management would like to transfer all of the risk to the builder. Which type of procurement contract would the organization use?

Options

  • ACost-plus contract.
  • BTurnkey contract.
  • CService contract.
  • DSolutions contract.