IIA
IIA-CIA-PART3 · Question #243
Which of the following is required in effective IT change management?
The correct answer is B. Change management follows a consistent process and is done in a controlled environment. You've hit your session limit · resets 10:20pm (America/New_York)
Question
Which of the following is required in effective IT change management?
Options
- AThe sole responsibility for change management is assigned to an experienced and competent IT
- BChange management follows a consistent process and is done in a controlled environment.
- CInternal audit participates in the implementation of change management throughout the
- DAll changes to systems must be approved by the highest level of authority within an organization.
How the community answered
(26 responses)- A19% (5)
- B69% (18)
- C4% (1)
- D8% (2)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)