According to lIA guidance on IT, which of the following plans would pair the identification of critical business processes with recovery time objectives?
The correct answer is C. The business Impact analysis plan. You've hit your session limit · resets 10:20pm (America/New_York)
Question
According to lIA guidance on IT, which of the following plans would pair the identification of critical business processes with recovery time objectives?
Options
- AThe business continuity management charter.
- BThe business continuity risk assessment plan.
- CThe business Impact analysis plan
- DThe business case for business continuity planning
How the community answered
(39 responses)- A10% (4)
- B8% (3)
- C79% (31)
- D3% (1)
Explanation