What is the primary risk associated with an organization adopting a decentralized structure?
The correct answer is C. Inconsistency in decision making. See the full explanation below for the reasoning.
Question
What is the primary risk associated with an organization adopting a decentralized structure?
Options
- AInability to adapt.
- BGreater costs of control function.
- CInconsistency in decision making.
- DLack of resilience.
How the community answered
(18 responses)- A6% (1)
- B6% (1)
- C72% (13)
- D17% (3)
Community Discussion