What is the primary risk associated with an organization adopting a decentralized structure?

The correct answer is C. Inconsistency in decision making. See the full explanation below for the reasoning.

Question

What is the primary risk associated with an organization adopting a decentralized structure?

Options

  • AInability to adapt.
  • BGreater costs of control function.
  • CInconsistency in decision making.
  • DLack of resilience.