IIA-CIA-PART2 · Question #140
After concluding a preliminary assessment, the engagement supervisor prepared a draft work program According to HA guidance which of the following would be tested by this program?
The correct answer is C. The process controls. According to IIA guidance, a draft work program prepared by the engagement supervisor after concluding a preliminary assessment would test the process controls. The work program outlines the specific procedures and steps the internal audit team will take to evaluate the…
Question
After concluding a preliminary assessment, the engagement supervisor prepared a draft work program According to HA guidance which of the following would be tested by this program?
Options
- AThe process objectives.
- BThe process risks
- CThe process controls
- DThe process scope
How the community answered
(35 responses)- A6% (2)
- B3% (1)
- C89% (31)
- D3% (1)
Explanation
According to IIA guidance, a draft work program prepared by the engagement supervisor after concluding a preliminary assessment would test the process controls. The work program outlines the specific procedures and steps the internal audit team will take to evaluate the effectiveness of the controls in place to mitigate identified risks.