As a Belt created a Process Map he realized there were multiple departments involved in this process so he added a feature to the map called ______________.

The correct answer is B. Swim Lanes. Swim Lanes (B) are the correct feature added to a Process Map when multiple departments are involved - they visually divide the map into horizontal or vertical bands, one per department, making it immediately clear which department is responsible for each step in the process. A…

Measure

Question

As a Belt created a Process Map he realized there were multiple departments involved in this process so he added a feature to the map called ______________.

Options

  • APassing Lanes
  • BSwim Lanes
  • CDepartment Dividers
  • DResponsibility Paths

How the community answered

(40 responses)
  • B
    93% (37)
  • C
    3% (1)
  • D
    5% (2)

Explanation

Swim Lanes (B) are the correct feature added to a Process Map when multiple departments are involved - they visually divide the map into horizontal or vertical bands, one per department, making it immediately clear which department is responsible for each step in the process.

  • A (Passing Lanes) is a highway driving term with no meaning in process mapping.
  • C (Department Dividers) sounds plausible but is not a recognized Lean/Six Sigma term.
  • D (Responsibility Paths) is fabricated terminology not used in any standard process mapping methodology.

Memory tip: Think of a swimming pool - each swimmer stays in their own lane. In a process map, each department stays in its own Swim Lane, so you always know who "owns" each step.