ICYB · Question #71
Training cost is $3,000 and a project required an initial investment of $12,000. If the project yields monthly savings of $1,800 beginning after 3 months, what is the payback period in months…
The correct answer is C. 11.33. Option C (11.33 months) is correct because the total investment is $3,000 + $12,000 = $15,000, and since savings don't begin until after month 3, you first add that 3-month delay, then calculate how long to recover the remaining balance: $15,000 ÷ $1,800 = 8.33 additional…
Question
Training cost is $3,000 and a project required an initial investment of $12,000. If the project yields monthly savings of $1,800 beginning after 3 months, what is the payback period in months (before money costs and taxes)?
Options
- A4.17
- B8.33
- C11.33
- D28.28
How the community answered
(25 responses)- A4% (1)
- B4% (1)
- C84% (21)
- D8% (2)
Explanation
Option C (11.33 months) is correct because the total investment is $3,000 + $12,000 = $15,000, and since savings don't begin until after month 3, you first add that 3-month delay, then calculate how long to recover the remaining balance: $15,000 ÷ $1,800 = 8.33 additional months, giving 3 + 8.33 = 11.33 months total.
Why the distractors fail:
- B (8.33) is the most tempting trap - it correctly divides $15,000 by $1,800 but ignores the 3-month period before any savings occur.
- A (4.17) results from using only one cost component (e.g., just the $3,000 training cost ÷ $1,800 × some factor), failing to combine both investment figures.
- D (28.28) likely comes from incorporating time value of money or interest rates, which the question explicitly excludes ("before money costs and taxes").
Memory tip: When a payback problem mentions a delay before cash flows begin, think of it as a two-part race - first wait for the starting gun (the delay period), then run to the finish line (investment ÷ savings rate). Add both legs together for the true payback period.
Topics
Community Discussion
No community discussion yet for this question.