ICYB · Question #107
Training cost $2,500 and a project required an initial investment of $23,500. If the project yields monthly savings of $2,500 beginning after 4 months, what is the payback period in months (before…
The correct answer is C. 14.4. Option C (14.4 months) is correct because the total investment is $2,500 (training) + $23,500 (project) = $26,000, and savings of $2,500/month don't begin until after a 4-month delay. Dividing $26,000 ÷ $2,500 gives 10.4 months of savings needed, then adding the 4-month waiting…
Question
Training cost $2,500 and a project required an initial investment of $23,500. If the project yields monthly savings of $2,500 beginning after 4 months, what is the payback period in months (before money costs and taxes)?
Options
- A7.2
- B10.4
- C14.4
- D28.8
How the community answered
(30 responses)- A10% (3)
- B7% (2)
- C80% (24)
- D3% (1)
Explanation
Option C (14.4 months) is correct because the total investment is $2,500 (training) + $23,500 (project) = $26,000, and savings of $2,500/month don't begin until after a 4-month delay. Dividing $26,000 ÷ $2,500 gives 10.4 months of savings needed, then adding the 4-month waiting period yields 14.4 months total.
Why the distractors fail:
- B (10.4) is the most tempting trap - it correctly divides $26,000 ÷ $2,500 but ignores the 4-month delay before savings start.
- A (7.2) likely results from omitting the training cost and the delay, using only a portion of the total investment.
- D (28.8) results from a double-counting or arithmetic error, roughly doubling the correct answer.
Memory tip: Think of payback in two stages - "How long until savings start?" (the delay) + "How long to recover the full investment once savings begin?" (total cost ÷ monthly savings). Always include all upfront costs (training, setup, etc.) and never forget to add any pre-savings delay to your savings-recovery period.
Topics
Community Discussion
No community discussion yet for this question.