nerdexam
Six_Sigma

ICGB · Question #16

Training cost is $4,000 and a project required an initial investment of $30,000. If the project yields monthly savings of $2,000 beginning after 3 months, what is the payback period in months…

The correct answer is B. 20. Option B (20 months) is correct because the total investment is $4,000 (training) + $30,000 (initial) = $34,000, and at $2,000/month in savings it takes 17 months of savings to recoup that amount - but since savings don't begin until after month 3, you add that 3-month delay…

Define

Question

Training cost is $4,000 and a project required an initial investment of $30,000. If the project yields monthly savings of $2,000 beginning after 3 months, what is the payback period in months (before money costs and taxes)?

Options

  • A10
  • B20
  • C27
  • D33

How the community answered

(30 responses)
  • A
    13% (4)
  • B
    77% (23)
  • C
    3% (1)
  • D
    7% (2)

Explanation

Option B (20 months) is correct because the total investment is $4,000 (training) + $30,000 (initial) = $34,000, and at $2,000/month in savings it takes 17 months of savings to recoup that amount - but since savings don't begin until after month 3, you add that 3-month delay: 17 + 3 = 20 months.

A (10) is wrong because it ignores both the training cost and the 3-month delay - likely from dividing only part of the investment by $2,000. C (27) results from a miscalculation such as adding the 3-month delay multiple times or using an incorrect total. D (33) similarly inflates the delay or misapplies when savings begin.

Memory tip: Payback = (Total Cost ÷ Monthly Savings) + Delay Months. Always add all costs first, then add any waiting period before savings kick in.

Topics

#payback period#financial analysis#project investment#ROI calculation

Community Discussion

No community discussion yet for this question.

Full ICGB Practice