nerdexam
Six_Sigma

ICBB · Question #91

ICBB Question #91: Real Exam Question with Answer & Explanation

The correct answer is B. $35. See the full explanation below for the reasoning.

Question

A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiring that the average cost of an internal critical raw material component be less than or equal to $4,200 in order to stay within budget. Using a sample of 35 first article components, a Mean of the new product upgrade price of $4,060, and a Standard Deviation of $98 was estimated. In order to increase the Long Term Z value to 4, what is the maximum long term variation in pricing the Belt can accept for his upgraded critical raw material component?

Options

  • A$20
  • B$35
  • C$70
  • D$110

Community Discussion

No community discussion yet for this question.

Full ICBB Practice
A Belt working in a supply chain environment has to make a... | ICBB Q#91 Answer | NerdExam