Question
A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt's effort requiring that the average cost of an internal critical raw material component be less than or equal to $2,800 in order to stay within budget. Using a sample of 55 first article components, a Mean of the new product upgrade price of $2,240 and a Standard Deviation of $120 was estimated. Based on the data provided, the Z value for the data assuming a Normal Distribution is?
Options
- A2.33
- B4.67
- C6.48
- D8.28