I40-420 · Question #191
An organization has purchased a new Order Entry application. One of the requirements is to convert an existing file of customer information to the new application. In the Development project…
The correct answer is C. 1 EI. You've hit your session limit · resets 5:20pm (America/New_York)
Question
An organization has purchased a new Order Entry application. One of the requirements is to convert an existing file of customer information to the new application. In the Development project functional size how is the conversion counted?
Options
- A1 ILF
- B1 EIF and 1 EI
- C1 EI
- DNot counted
How the community answered
(47 responses)- A4% (2)
- B11% (5)
- C70% (33)
- D15% (7)
Explanation