I40-420 · Question #170
An enhancement project does not change the functional sizing of the application, but just the GSCs. The application's aAFP was 101 FPs, with a VAF of 1.01. The following generic system…
The correct answer is C. 104. You've hit your session limit · resets 5:20pm (America/New_York)
Question
An enhancement project does not change the functional sizing of the application, but just the GSCs. The application's aAFP was 101 FPs, with a VAF of 1.01. The following generic system characteristics are changed as described: a) Flexible query and report facility was provided that can handle simple requests; now this facility can handle complex requests b) Business control data was kept in tables that are maintained by the user with on-line interactive processes, but changes take effect only on the next business cycle; now changes can take effect immediately What is the aAFPA?
Options
- A100
- B101
- C104
- D106
How the community answered
(38 responses)- A3% (1)
- B11% (4)
- C71% (27)
- D16% (6)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)