I40-420 · Question #148

The team has been asked to size the software associated with porting the Order Management system from one operating system to a different operating system. The project includes a one-time data…

The correct answer is C. FP approach can be used for sizing the data conversion activity. FP approach is not suitable for. You've hit your session limit · resets 5:20pm (America/New_York)

Question

The team has been asked to size the software associated with porting the Order Management system from one operating system to a different operating system. The project includes a one-time data conversion activity. Which of the following is true?

Options

  • AFP approach can be used to size both the operating system upgrade and the data conversion
  • BFP approach can be used to size the operating system upgrade. The data conversion activity cannot
  • CFP approach can be used for sizing the data conversion activity. FP approach is not suitable for
  • DFP approach cannot be applied to size either the operating system upgrade or the one-time data

How the community answered

(20 responses)
  • A
    15% (3)
  • B
    5% (1)
  • C
    75% (15)
  • D
    5% (1)

Explanation