A Purchasing application prior to the enhancement had 204 FP. An enhancement project contributed the following: Added FP = 12 Deleted FP = 0 Change After FP = 31 Conversion FP = 0 What is the EFP?

The correct answer is C. 43. You've hit your session limit · resets 5:20pm (America/New_York)

Question

A Purchasing application prior to the enhancement had 204 FP. An enhancement project contributed the following:

Added FP = 12 Deleted FP = 0 Change After FP = 31 Conversion FP = 0 What is the EFP?

Options

  • A13
  • B42
  • C43
  • D236