HP
HPE6-A79 · Question #46
Refer to the exhibit. After a recent power outage where MM1 is located, the network administrator could not perform configuration tasks on Mobility Controllers (MC) for several hours. Which…
The correct answer is C. Reduce the VRRP priority to 90 and restart the process in MM2. Explanation/Reference:
Deploying and Integrating Aruba Mobility Solutions
Question
Refer to the exhibit. After a recent power outage where MM1 is located, the network administrator could not perform configuration tasks on Mobility Controllers (MC) for several hours. Which configuration tasks must the network administrator do before applying the script in order to successfully deploy L2 MM redundancy and prevent any other control plane outage?
Exhibit
Options
- AConfirm that the VRRP and master redundancy keys are the same.
- BChange the VIP address of ther VRRP process 140 to 10.254.10.15.
- CReduce the VRRP priority to 90 and restart the process in MM2.
- DEnable the MM database synchronization in MM2.
How the community answered
(38 responses)- A24% (9)
- B5% (2)
- C55% (21)
- D16% (6)
Explanation
Explanation/Reference:
Topics
#MM redundancy#VRRP priority#L2 redundancy#control plane
Community Discussion