HPE6-A47 · Question #51
Refer to the exhibits. Exhibit 1 shows the logical plan, and Exhibit 2 shows the BOM created with IRIS. An architect plans to propose two 5406Rzl switches as a VSF fabric for a campus network core…
The correct answer is B. Change the v2 modules to v3 modules. See the full explanation below for the reasoning.
Question
Refer to the exhibits. Exhibit 1 shows the logical plan, and Exhibit 2 shows the BOM created with IRIS. An architect plans to propose two 5406Rzl switches as a VSF fabric for a campus network core. Which issue with the plan should the architect correct? Exhibit 1 Exhibit 2
Exhibit
Options
- AAdd two QSPF+ MP0 SR4 transceivers.
- BChange the v2 modules to v3 modules.
- CAdd stacking modules and cables.
- DChange the power supply type.
How the community answered
(60 responses)- A17% (10)
- B70% (42)
- C10% (6)
- D3% (2)