nerdexam
HP

HPE6-A45 · Question #23

Switch-1 has a power issue that causes it to fail. When Switch-1 comes back up, endpoints lose connectivity for a few minutes. The network administrator decides to use this command: Switch-1# vlan…

The correct answer is B. Switch-1 now waits to take over as Master if it fails and recovers. This should prevent the connectivity issues from occurring again. See the full explanation below for the reasoning.

Question

Switch-1 has a power issue that causes it to fail. When Switch-1 comes back up, endpoints lose connectivity for a few minutes. The network administrator decides to use this command: Switch-1# vlan 10 vrrp vrid 10 preempt-delay-time 120 Exhibit 2 shows the VRRP configuration just after the change. What is the effect of this change?

Options

  • ASwitch-1 and Switch-2 both become Master in their own VRRP virtual router due to the delay timer mismatch. The mismatch must be fixed.
  • BSwitch-1 now waits to take over as Master if it fails and recovers. This should prevent the connectivity issues from occurring again.
  • CSwitch-1 immediately becomes Master in the VRRP virtual router. This would cause Switch-2 to take over as Master for VLAN 1.
  • DSwitch-1 continues to act as it did before the preempt delay time was set. Administrators must plan additional changes to fix the issue.

How the community answered

(33 responses)
  • A
    12% (4)
  • B
    79% (26)
  • C
    6% (2)
  • D
    3% (1)