HP
HPE6-A45 · Question #169
Refer to the exhibit. What is one issue with the current configuration planned for VLAN 20 on the switch?
The correct answer is D. The controller must not enable jumbo frames. See the full explanation below for the reasoning.
Question
Refer to the exhibit. What is one issue with the current configuration planned for VLAN 20 on the switch?
Options
- AVLAN 20 must have an IP address.
- BVLAN 20 cannot have an IP address in the same subnet as the controller.
- CThe Aruba Mobility controller must enable jumbo frames.
- DThe controller must not enable jumbo frames.
How the community answered
(29 responses)- A3% (1)
- B10% (3)
- C3% (1)
- D83% (24)
Community Discussion
No community discussion yet for this question.