Question

A company requires distribution layer switches that can provide Layer 2 and Layer 3 redundancy. The exhibit shows the proposal for these switches. Which change to the exhibit is needed to meet the company's requirements?

Options

  • AThe proposed switches should be replaced with switches such as the Aruba 2930M to support the backplane stacking technology.
  • BVSFM should be implemented instead of backplane stacking to support the Layer 3 redundancy requirements.
  • CLink aggregation should be configured with two LACP trunks from the LAPs to redundancy requirements and backplane stacking limitations.
  • DThe proposed switches should be replaced with switches that support VSF to support the required distance between stack members.