nerdexam
HP

HPE0-S59 · Question #51

Your customer manages an HPE Synergy platform using HPE OneView 5.6. To leverage new functionalities, the customer wants to update HPE OneView to version 61. Which statement about this update…

The correct answer is A. To update to 6,1, the customer has to first update to 6 0, which is a milestone edition. When updating HPE OneView to version 6.1, it is necessary to first update to version 6.0, which is a milestone edition. Milestone editions include significant architectural changes and updates that are prerequisites for subsequent versions. This step ensures that the system is…

Manage and Maintain HPE Compute Solutions

Question

Your customer manages an HPE Synergy platform using HPE OneView 5.6. To leverage new functionalities, the customer wants to update HPE OneView to version 61. Which statement about this update process is true?

Options

  • ATo update to 6,1, the customer has to first update to 6 0, which is a milestone edition.
  • BThe customer can update directly to 6,1, but HPE OneView downtime will be longer.
  • CBefore updating to 6,1, customer should increase memory size on the HPE Composer.
  • DThe customer must check the HPE Composer version, as 61 is supported only with HPE

How the community answered

(28 responses)
  • A
    89% (25)
  • B
    4% (1)
  • C
    7% (2)

Explanation

When updating HPE OneView to version 6.1, it is necessary to first update to version 6.0, which is a milestone edition. Milestone editions include significant architectural changes and updates that are prerequisites for subsequent versions. This step ensures that the system is properly prepared and compatible with the new features and improvements introduced in version 6.1.

Topics

#HPE OneView update#version upgrade#milestone release#update path

Community Discussion

No community discussion yet for this question.

Full HPE0-S59 Practice