HPE0-P26 · Question #52

You are designing a custom HPE GreenLake solution and have created solution BOMs. Is this the next step in the process? Solution: Present your business case to the customer.

The correct answer is A. Yes. After creating solution BOMs, presenting the business case to the customer is indeed the logical next step in the HPE GreenLake custom solution design process. The BOM (Bill of Materials) provides the detailed component and cost foundation needed to construct a compelling…

Configure HPE GreenLake Core Solutions

Question

You are designing a custom HPE GreenLake solution and have created solution BOMs. Is this the next step in the process? Solution: Present your business case to the customer.

Options

  • AYes
  • BNo

How the community answered

(27 responses)
  • A
    93% (25)
  • B
    7% (2)

Explanation

After creating solution BOMs, presenting the business case to the customer is indeed the logical next step in the HPE GreenLake custom solution design process. The BOM (Bill of Materials) provides the detailed component and cost foundation needed to construct a compelling business case that demonstrates value, ROI, and total cost of ownership to the customer. Without completing the BOM first, you would lack the specifics required to make a credible financial and technical argument.

Why B is wrong: Choosing "No" incorrectly implies there is an intermediate step between BOM creation and the customer presentation, but the standard HPE GreenLake design workflow moves directly from finalizing BOMs to presenting the business case.

Memory tip: Think of it as "Build, then Pitch" - you Build the BOM (the "what and how much"), then Pitch the business case (the "why you should buy it"). The BOM feeds directly into the business case, so they flow sequentially with no gap.

Topics

#BOM design#business case#sales process#custom GreenLake solution