An integrator is validating a design for an HPE 3PAR StoreServ solution. The assessment document shows that there is structured cabling between the rack the array will be installed in and the racks…

The correct answer is B. The SC connectors must be replaced by LC connectors. See the full explanation below for the reasoning.

Question

An integrator is validating a design for an HPE 3PAR StoreServ solution. The assessment document shows that there is structured cabling between the rack the array will be installed in and the racks with the SAN switches. The fiber segments between the racks are documented as being 50 micron OM2 and are terminated with SC connectors. What needs to be considered when validating this design?

Options

  • A3PAR arrays must be directly connected to SAN switches.
  • BThe SC connectors must be replaced by LC connectors.
  • COM2 Fiber cables are not supported for 8 Gbps.
  • DFiber segments cannot mix OM2 and OM4 cables.

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    83% (20)
  • C
    4% (1)
  • D
    8% (2)