A storage integrator is planning the implementation of a single HPE StoreOnce 3100. How many power cords are required to be connected to PDU from this storage system, when power supply kit was…

The correct answer is B. 2. https://h20195.www2.hpe.com/v2/GetPDF.aspx/c04328820.pdf

Basic Configuration and Management

Question

A storage integrator is planning the implementation of a single HPE StoreOnce 3100. How many power cords are required to be connected to PDU from this storage system, when power supply kit was ordered?

Options

  • A0
  • B2
  • C4
  • D6

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    74% (20)
  • C
    4% (1)
  • D
    7% (2)

Explanation

https://h20195.www2.hpe.com/v2/GetPDF.aspx/c04328820.pdf

Topics

#StoreOnce 3100#power supply#PDU#storage system