HP
HP0-Y37 · Question #79
You want to migrate a Cisco network from PVST+ to MSTP and complete the migration with the least amount of downtime. Place the migration steps to meet these goals in the correct sequence.
The correct sequence of migration steps is: Step 1: Configure MSTP parameters on switches Step 2: Change to MSTP mode on edge Step 3: Change to MSTP mode on distribution Step 4: Remove backbonefast, uplinkfast Step 5: Configure MSTP priorities on distribution
Perform Network Infrastructure Migration
Question
You want to migrate a Cisco network from PVST+ to MSTP and complete the migration with the least amount of downtime. Place the migration steps to meet these goals in the correct sequence.
Explanation
The correct sequence of migration steps is: Step 1: Configure MSTP parameters on switches Step 2: Change to MSTP mode on edge Step 3: Change to MSTP mode on distribution Step 4: Remove backbonefast, uplinkfast Step 5: Configure MSTP priorities on distribution
Topics
#PVST+ to MSTP migration#spanning tree#minimal downtime#migration sequencing
Community Discussion
No community discussion yet for this question.