What should be done in preparing the SAN for production to help minimize risk and maximize the probability of success?

The correct answer is D. deploy in phases. See the full explanation below for the reasoning.

Question

What should be done in preparing the SAN for production to help minimize risk and maximize the probability of success?

Options

  • Athoroughly test individual components before deployment
  • Bdetermine the number of fabric zones required to support your environment
  • Cutilize fibre channel switches from only one vendor
  • Ddeploy in phases

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    9% (4)
  • D
    84% (36)