H13-629_V3.0 · Question #847

A company deployed a set of Huawei distributed storage in Data Center A and Data Center B, mainly using block services to carry database, virtual machine and other application-related services, and…

The correct answer is A. It is recommended to deploy the arbitration server at the third-party site B. It is recommended that database applications use active-active consistency groups C. It is recommended that the distance between data center A and data center B is less than 100. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

A company deployed a set of Huawei distributed storage in Data Center A and Data Center B, mainly using block services to carry database, virtual machine and other application-related services, and using the active-active features of block services in conjunction with upper-layer applications to ensure business continuity. Which of the following options are correct for this active-active scenario? (Multiple choice)

Options

  • AIt is recommended to deploy the arbitration server at the third-party site
  • BIt is recommended that database applications use active-active consistency groups
  • CIt is recommended that the distance between data center A and data center B is less than 100
  • DIt is recommended to use FC networking for arbitration links

How the community answered

(58 responses)
  • A
    78% (45)
  • D
    22% (13)

Topics

#active-active storage#HyperMetro#arbitration server#distributed block services

Community Discussion

No community discussion yet for this question.