To ensure data security and business continuity, the company has built a primary and backup disaster recovery system. The construction information of the disaster recovery system is as follows: (1)…

The correct answer is B. False. See the full explanation below for the reasoning.

Data Protection and Business Continuity Solution Design

Question

To ensure data security and business continuity, the company has built a primary and backup disaster recovery system. The construction information of the disaster recovery system is as follows:

(1) The production center and disaster recovery center use asynchronous remote control. (2) Business data synchronization time is about 8 hours per day. (3) The daily data increment is about 1500 MB. (4) The cycle is once every 4 hours. Based on the above background assessment, the company's IT technicians concluded that a disaster recovery network bandwidth greater than 0.5 Mbps would meet the requirements.

Options

  • ATrue
  • BFalse

How the community answered

(32 responses)
  • A
    16% (5)
  • B
    84% (27)