When using Huawei's all-flash storage HyperReplication feature to conduct a disaster recovery drill, which of the following analyses of the drill operation steps are correct? (Multiple choice)
The correct answer is A. Failure of remote pair splitting will cause subsequent disaster recovery operations to fail B. After the remote pair splits, master-slave switching is required C. Before performing disaster recovery operations, you need to split the remote pair D. After the remote pair split is completed, the slave resource protection needs to be cancelled. See the full explanation below for the reasoning.
Data Protection and Business Continuity Solution Design
Question
When using Huawei's all-flash storage HyperReplication feature to conduct a disaster recovery drill, which of the following analyses of the drill operation steps are correct? (Multiple choice)
Options
- AFailure of remote pair splitting will cause subsequent disaster recovery operations to fail
- BAfter the remote pair splits, master-slave switching is required
- CBefore performing disaster recovery operations, you need to split the remote pair
- DAfter the remote pair split is completed, the slave resource protection needs to be cancelled
How the community answered
(14 responses)- A100% (14)
Topics
#HyperReplication#DR drill#remote pair splitting#master-slave switching