A company has deployed Huawei BCManager in two data centers A and B for disaster recovery configuration and management. It plans to use eReplication to perform disaster recovery tests on the two…
The correct answer is A. Disaster recovery host scans disk B. Switching relationship D. Start the disaster recovery application. See the full explanation below for the reasoning.
Data Protection and Business Continuity Solution Design
Question
A company has deployed Huawei BCManager in two data centers A and B for disaster recovery configuration and management. It plans to use eReplication to perform disaster recovery tests on the two sites regularly. Which of the following items are the steps involved in the company's disaster recovery test? (Multiple choice)
Options
- ADisaster recovery host scans disk
- BSwitching relationship
- CMap snapshots to disaster recovery hosts
- DStart the disaster recovery application
How the community answered
(51 responses)- A82% (42)
- C18% (9)