Which of the following tasks need to be completed during the planning stage of a project? (Choose two.)

The correct answer is B. Know the project background D. Make dear the requirements of a project. See the full explanation below for the reasoning.

Question

Which of the following tasks need to be completed during the planning stage of a project? (Choose two.)

Options

  • AWork out the technical design
  • BKnow the project background
  • CDetermine the model of network devices in the project
  • DMake dear the requirements of a project
  • EPlan IP addresses

How the community answered

(61 responses)
  • A
    7% (4)
  • B
    72% (44)
  • C
    16% (10)
  • E
    5% (3)

Community Discussion

No community discussion yet for this question.