The project scope can be determined from three aspects. Which of the following is not included?
The correct answer is C. Investment budget of the project. See the full explanation below for the reasoning.
Question
The project scope can be determined from three aspects. Which of the following is not included?
Options
- AFunctions and modules to be realized by the project
- BGeographic range of the network
- CInvestment budget of the project
- DResponsibility division between the project and other matching systems
How the community answered
(19 responses)- A5% (1)
- B5% (1)
- C79% (15)
- D11% (2)