You are the project manager of the NJJ project. Your enterprise environmental factors require that you establish certain risk management rules regarding low risks within your project. What is the…

The correct answer is D. These risks should be placed on a watchlist for future monitoring. Low probability and low impact risks do not justify active response planning, so they are placed on a watchlist for periodic re-evaluation.

Risk Management & Compliance

Question

You are the project manager of the NJJ project. Your enterprise environmental factors require that you establish certain risk management rules regarding low risks within your project. What is the best policy for risks with low probability and low impact in the project management?

Options

  • AThese risks should be placed in the risk register.
  • BThese risks should be identified, but dismissed.
  • CThese risks should be accepted.
  • DThese risks should be placed on a watchlist for future monitoring.

How the community answered

(61 responses)
  • A
    3% (2)
  • B
    2% (1)
  • D
    95% (58)

Why each option

Low probability and low impact risks do not justify active response planning, so they are placed on a watchlist for periodic re-evaluation.

AThese risks should be placed in the risk register.

Simply entering a risk in the risk register does not specify a management approach and is insufficient on its own for low-level risks.

BThese risks should be identified, but dismissed.

Dismissing identified risks entirely removes the ability to detect if their probability or impact escalates later in the project.

CThese risks should be accepted.

Acceptance is a valid risk response, but it is typically applied to risks where no cost-effective response exists - a watchlist is the more precise PMBOK recommendation for low/low risks.

DThese risks should be placed on a watchlist for future monitoring.Correct

PMBOK identifies a watchlist as the appropriate handling for low-priority risks that fall below the threshold for active management. Placing these risks on a watchlist ensures they remain visible and can be re-evaluated if their probability or impact changes over time, without consuming response-planning resources.

Concept tested: Risk response strategy for low-priority risks

Topics

#risk watchlist#low probability risk#risk register#risk acceptance policy