GSLC · Question #240
Nancy is the project manager for a new construction project. There are several occupational safety codes, which must be included in the project requirements. These requirements are nonnegotiable and t
The correct answer is A. Cost of quality. Mandatory safety code compliance costs - including inspections and training - are classified as cost of quality because they represent planned conformance expenditures required to meet defined standards.
Question
Nancy is the project manager for a new construction project. There are several occupational safety codes, which must be included in the project requirements. These requirements are nonnegotiable and the customer must pay for the safety measures, inspections, and training for the project team. What term best describes the cost associated with these safety requirements?
Options
- ACost of quality
- BCost of doing business
- CCost of risk avoidance
- DCost of risk mitigation
How the community answered
(53 responses)- A92% (49)
- B4% (2)
- C2% (1)
- D2% (1)
Why each option
Mandatory safety code compliance costs - including inspections and training - are classified as cost of quality because they represent planned conformance expenditures required to meet defined standards.
Cost of quality in project management encompasses all costs incurred to ensure deliverables meet requirements, including prevention costs (training), appraisal costs (inspections), and conformance to regulatory standards; mandatory occupational safety codes are non-negotiable quality requirements, so all associated spending falls directly under this category.
Cost of doing business is not a formal project management or PMBOK term and does not specifically describe the structured categorization of compliance-driven quality expenditures.
Cost of risk avoidance refers to expenses taken to eliminate a risk entirely by not pursuing a risky activity, which does not accurately describe mandatory regulatory safety compliance costs.
Cost of risk mitigation refers to reducing the probability or impact of a risk event, whereas these safety requirements are nonnegotiable conformance standards - a quality concern rather than a risk mitigation strategy.
Concept tested: Cost of quality - conformance costs in project management