GSLC · Question #46
Maria works as a Risk Analysis Manager for Gentech Inc. She starts a new IT project. Which of the following phases of her project development process is most suitable for including risk analysis?
The correct answer is B. Project initiation. Risk analysis is most appropriately included during the project initiation phase so that risks can be identified and planned for before significant resources or commitments are made.
Question
Maria works as a Risk Analysis Manager for Gentech Inc. She starts a new IT project. Which of the following phases of her project development process is most suitable for including risk analysis?
Options
- AImplementation planning
- BProject initiation
- CSystem construction
- DRequirements definition
How the community answered
(42 responses)- A5% (2)
- B93% (39)
- D2% (1)
Why each option
Risk analysis is most appropriately included during the project initiation phase so that risks can be identified and planned for before significant resources or commitments are made.
Implementation planning occurs after the project has already been approved and scoped, which is too late to influence foundational risk-based decisions.
Project initiation is the earliest phase where the project scope, objectives, and feasibility are being defined, making it the ideal time to conduct risk analysis. Identifying risks at this stage allows decision-makers to determine whether to proceed, adjust scope, or allocate risk mitigation resources before major investments are committed. Early risk analysis ensures risk management is built into the project foundation rather than added as an afterthought.
System construction is a late execution phase where major architectural and design decisions have already been made, significantly limiting the options available for risk mitigation.
Requirements definition follows project initiation and is focused on detailing functional needs rather than performing the broader feasibility and risk assessment appropriate to initiation.
Concept tested: Risk analysis placement in project lifecycle
Source: https://csrc.nist.gov/publications/detail/sp/800-30/rev-1/final
Topics
Community Discussion
No community discussion yet for this question.