You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will…

The correct answer is A. Qualitative analysis. Qualitative risk analysis uses probability and impact ratings to prioritize identified risks, producing a ranked list that flags which risks require more in-depth quantitative analysis.

Risk Management & Compliance

Question

You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?

Options

  • AQualitative analysis
  • BQuantitative analysis
  • CRisk identification
  • DEstimate activity duration

How the community answered

(48 responses)
  • A
    92% (44)
  • B
    2% (1)
  • C
    2% (1)
  • D
    4% (2)

Why each option

Qualitative risk analysis uses probability and impact ratings to prioritize identified risks, producing a ranked list that flags which risks require more in-depth quantitative analysis.

AQualitative analysisCorrect

Qualitative risk analysis applies a relative scale to assess each identified risk's probability of occurrence and its potential impact, generating a prioritized list that directly answers the question of which risks need further, more rigorous numerical analysis through quantitative methods.

BQuantitative analysis

Quantitative risk analysis numerically models the effect of high-priority risks on project objectives and is the step performed after qualitative analysis has already identified which risks warrant deeper examination.

CRisk identification

Risk identification is the process of discovering and documenting potential risks, not evaluating or ranking them to determine which need further analysis.

DEstimate activity duration

Estimating activity duration is a schedule management activity used to calculate the time needed for project work and is unrelated to the risk management process.

Concept tested: Qualitative risk analysis for prioritizing risks

Topics

#qualitative risk analysis#risk identification#risk prioritization#risk management

Community Discussion

No community discussion yet for this question.

Full GSLC Practice