GSLC · Question #452
You are advising a school district on disaster recovery plans. In case a disaster affects the main IT centers for the district they will need to be able to work from an alternate location. However…
The correct answer is D. Cold site. A cold site is the lowest-cost disaster recovery option, providing only basic facility infrastructure with no pre-installed equipment, making it the most appropriate choice for a budget-constrained organization.
Question
You are advising a school district on disaster recovery plans. In case a disaster affects the main IT centers for the district they will need to be able to work from an alternate location. However, budget is an issue. Which of the following is most appropriate for this client?
Options
- AWarm site
- BHot site
- COff site
- DCold site
How the community answered
(27 responses)- A15% (4)
- B7% (2)
- C4% (1)
- D74% (20)
Why each option
A cold site is the lowest-cost disaster recovery option, providing only basic facility infrastructure with no pre-installed equipment, making it the most appropriate choice for a budget-constrained organization.
A warm site includes some pre-installed hardware and network connectivity but requires additional configuration and data restoration, making it more costly to maintain than a cold site.
A hot site is a fully operational mirror of the primary environment capable of near-immediate failover, but it is the most expensive DR option and unsuitable for a tight budget.
Off site is not a formally defined disaster recovery tier with a specific readiness or cost profile in the same way that hot, warm, and cold sites are, so it does not represent a valid comparative option here.
A cold site offers a physical space with basic utilities such as power, cooling, and network connectivity, but no pre-configured hardware, software, or data. It is the least expensive disaster recovery tier because the organization is not paying to maintain duplicate systems - only the facility itself - which directly addresses the school district's budget constraint, though recovery time will be significantly longer since equipment must be obtained and configured after a disaster occurs.
Concept tested: Disaster recovery site types - cost vs recovery time tradeoff
Source: https://www.ready.gov/it-disaster-recovery-plan
Topics
Community Discussion
No community discussion yet for this question.